摘要众所周知,中国是一个煤炭资源大国,这一基本国情决定了我国煤炭产业的发达,因此我国的煤矿众多,而贯通测量无疑一个煤矿的生产过程中必不可少的组成部分。贯通测量方案设计的好坏直接影响整个工程的施工质量。本文针对徐州市垞城煤矿的的实际情况进行了两井间巷道贯通测量设计,并给出了预计误差,最后总结了一些提高测量精度的外业优化措施。34379 毕业论文关键词: 贯通测量,两井定向,误差预计
Abstract
As is known to all, China has the largest coal resources in the world, this basic national conditions determines the coal industry in our country are developed, China has so many coal mines, and the technology of breakthrough survey is a indispensable part of the production process of every coal mine. The project design of breakthrough survey directly affect the construction quality of the whole project. Based on the actual condition of coal mine of Xuzhou,I design the project and give the estimated error. Finally I summarizes some field advices and measures to improve measurement accuracy.
Key words:breakthrough survey, orientation based two mines, error estimation.
目 录
摘要Ⅰ
AbstractⅡ
1 绪 论 4
1.1 选题背景以及研究意义 4
1.2 本课题国内外研究现状及发展方向 4
1.3 主要研究目的和研究内容 5
2 贯通工程概况 5
2.1 贯通测量的目的和任务 5
2.2贯通要求 6
2.3坐标系统与高程系统 6
3 贯通测量方案简述 6
3.1地面控制测量 7
3.1.1 地面平面控制测量 7
3.1.2地面高程控制测量 10
3.2 矿井联系测量 10
3.2.1 概述 10
3.2.2 平面坐标联系测量 10
3.2.3 高程联系测量 11
3.3 井下控制测量 13
3.3.1 井下平面控制测量 13
3.3.2 井下高程控制测量 14
4 贯通测量误差预计 16
4.1贯通平面误差预计 16
4.2巷道高程误差预计 21
4.3结论及相关建议 22
5 结束语 23