摘要连云港徐圩港区预制厂构件出运码头施工组织设计在编制过程中认真参考 并研究了各项水文资料和施工现场条件,本着强化质量管理、合理安排工期、降 低资源消耗的原则,尽可能的优化了施工方案。充分利用公司已有的和国内先进 的生产设备和船机设备,投入足够满足本工程施工强度要求的施工机械设备,组 织进行机械化和专业化施工,以确保本工程能够在工期内保质保量完成。 78250

毕业论文关键词:沉箱码头;施工组织设计;施工工艺。

Abstract The construction organization design of Lianyungang XuWei port precast component factory shipment wharf during the process of compiling is designed to give serious consideration according to the hydrological data and construction site

conditions,   with   the  purpose  of  strengthening  quality  management , make  the

arrangement of time reasonable , reducing the consumption of resources, as far as possible to optimize the construction scheme。 Making full use of the  existing company and domestic advanced production equipment and ship machine equipment, investing enough to meet the requirements of the strength of the construction of the project of construction machinery and equipment machinery and professional construction organization, to ensure that the works can within the time limit for a project to complete the quality and quantity。

Keywords: caisson quay;construction organization design;construction technology。

目录

第一章  绪论 1

1。1 施工组织设计的意义 1

1。2 编制说明 1

1。3 编制依据 1

1。4 编制原则 2

第二章  工程概况 3

2。1 水位资料 3

2。2 海流资料 3

2。3 风 4

2。4 气温 6

2。5 降水 6

2。6 工程地质条件 7

第三章  施工总平面布置 9

3。1 布置原则 9

3。2 施工总平面布置 9

3。3 施工总平面布置图 10

第四章  分部分项工程的主要工程量 12

4。1 工程量汇总 12

4。2 工期安排 17

4。3 船机、测量器具使用统计 18

4。4 施工横道图 20

第五章  测量工程 21

5。1 控制点的确认 21

5。2 平面控制系统 21

5。3 高程控制系统 21

5。4 施工过程中的测量控制 21

5。5 测量点平面布置示意图 22

5。6 测量仪器汇总 22

第六章  基槽挖泥 23

6。1 总体配置 23

6。2 施工布置 24

6。3 分项工程简略图

上一篇:滁州港重力式码头设计+图纸
下一篇:射阳港3000吨级散货码头设计及施工组织设计+图纸

江阴港申夏港区联合铁钢...

上海港张华浜港区9#集装箱...

秦皇岛港区5000吨级重力式...

青岛港董家口港区沉箱码头设计+图纸

泉州港东石港区集装箱码头+CAD图纸

泉州港东石港区集装箱码头设计+图纸

深水青岛港董家口港区防波堤工程设计+图纸

国内外无刷直流电动机研究现状

《醉青春》导演作品阐述

浅谈新形势下妇产科护理...

拉力采集上位机软件开发任务书

浅谈传统人文精神茬大學...

谷度酒庄消费者回访调查问卷表

中国古代秘书擅权的发展和恶变

辩护律师的作证义务和保...

多元化刑事简易程序构建探讨【9365字】

高校网球场馆运营管理初探【1805字】